Tomorrow is the first day of construction – we are calling it “week zero” because we are stretching the work weekends from the original design of two to three. We needed to schedule it this way because the foundation has to be poured before the first work weekend. In order to pour the slab, we have to grade (thanks to MJ Ross), lay pipe (thanks Ferguson and Jack’s All American Plumbing), run some electrical line (thanks CED), set the rebar (thanks B&B Steel), form the slab (thanks to Hayward Lumber), inspect (thanks to SLO county), and pour the concrete (thanks CalPortland). Even with all this work there will only be a minimum crew on site.
We start tomorrow!!!
May 7, 2010 by Liz Schlemer