Although when we started this project we only wanted to work for 2 weekends (6 days), as a class we decided in order to accomplish the scope we have laid out we needed to work for two extra days. Our plan was to dig the pad on Saturday, May 7, build the form for the concrete on Sunday, inspection on Monday morning, rough plumbing on Monday afternoon, and pour the concrete on Tuesday. It is Wednesday, and without going into the gory details of why we haven’t accomplish all of this, let’s just say we are a bit behind. The front pad is done; the back pad is partially formed.
All of this to say we are learning much: Time estimates are ALWAYS wrong, precedence in activities are critical, conflict surfaces easily when we are tired and discouraged, contractors are the ONLY reason this project is moving ahead, and perseverance and hope go a long way to keep us motivated.
We can’t say enough thank you’s to our supporters. Look for their ads in the New Times, Ag Circle magazine, on this website, and on our banner at the job site.
-Liz